PoG Pipelines Engineering Assessments

PoG Pipelines Engineering Assessments

Benefits
Through detailed engineering assessments of the Perseus over Goodwyn (PoG) flowlines, Atteris were able to provide an accurate evaluation of the current status of the assets, as well as recommendations on the remaining operational life to ensure safe operation.
Background
Woodside Energy Limited operates the Perseus gas field located approximately 20 km North-East of the Goodwyn A platform, on the North West Shelf off Western Australia. The field consists of four subsea wells tied back to the GWA platform.
Work Performed by Atteris

Atteris was initially engaged to perform a review of survey data for the PoG flowline spoolpieces to evaluate for signs of axial walking. During this process it was determined that as-built dimensions were not used in the original survey comparison, resulting in considerable discrepancy in the survey results originally provided to Woodside. Using a combination of the survey data and as-installed coordinates of fixed references, Atteris derived the correct as-built dimensions of the spools, and using this information, were able to accurately assess the flowlines for signs of axial walking.

Based on the results of this work, detailed engineering assessments have been performed on two spoolpieces. A combination of Abaqus and Autopipe Finite Element Analysis (FEA) softwares were used to accurately model the behaviour of the flowline during shutdown/startup cycles, and the effect that these cycles had on the spoolpieces

Through the use of as-built material properties, challenging of original design criteria, recent pipeline surveys and the operational history of the assets, Atteris was able to provide the client reassurance on the current state of the PoG assets, as well as recommendations on the future operation of the field.

left arrow
right arrow
Download PDF
Share on facebook
Share on twitter
Share on linkedin
resources

Related Posts

Seawater Intake and Outfall
CASE STUDIES
Seawater Intake and Outfall
  • Tags:
  • Energy Transition
  • HDD
  • Shore Crossing
  • Tunnelling
Read More
Maitland to Burrup Subsea Corridor Assessment
CASE STUDIES
Maitland to Burrup Subsea Corridor Assessment
  • Tags:
  • Shore Approach
  • Shore Crossing
  • Subsea Pipeline
Read More
Simpson Pipeline – Decommissioning Stability Study
CASE STUDIES
Simpson Pipeline – Decommissioning Stability Study
  • Tags:
  • Decommissioning
  • On-bottom Stability
  • Subsea Pipeline
Read More