Benefits
The involvement from Atteris resulted in a cost-effective and successfully completed HDD shore crossing installation, and a pipeline section which can be safely and reliably operated.
Background
Quadrant Energy (formerlly Apache Energy) engaged Atteris to undertake the design of the 2 km, 16 inch diameter pipeline section across the shoreline for the Reindeer Gas Field Development, Northwest Shelf, Western Australia.
Work Performed by Atteris

Atteris’ scope of work included:

  • Performing a geological engineering study of the selected area
  • Develop a scope of work for a geotechnical survey
  • Design the shore crossing, based on a horizontal directional drilling (HDD) solution; 1.85 km HDD section plus pipeline tail-end
  • Pipeline design, including mechanical design, coating selection, CP design and hydrodynamic stability design
  • Pipeline installation engineering assessment
  • Provision of engineering input into the tender documents for construction
  • Review of construction bids (technical elements)
  • Provision of on-site engineering support during construction
left arrow
right arrow
Download PDF
Share on facebook
Share on twitter
Share on linkedin
resources

Related Posts

Seawater Intake and Outfall
CASE STUDIES
Seawater Intake and Outfall
  • Tags:
  • Energy Transition
  • HDD
  • Shore Crossing
  • Tunnelling
Read More
Maitland to Burrup Subsea Corridor Assessment
CASE STUDIES
Maitland to Burrup Subsea Corridor Assessment
  • Tags:
  • Shore Approach
  • Shore Crossing
  • Subsea Pipeline
Read More
Simpson Pipeline – Decommissioning Stability Study
CASE STUDIES
Simpson Pipeline – Decommissioning Stability Study
  • Tags:
  • Decommissioning
  • On-bottom Stability
  • Subsea Pipeline
Read More