Subsea & Pipelines Final Investment Decision

Subsea & Pipelines Final Investment Decision

Benefits
Atteris assisted its client (a non-operating JV partner) by assessing the subsea and pipeline (SS&PL) aspects of the project’s FID package. Atteris’ findings enabled our client to challenge its JV partner’s design with a number of technical, cost and schedule item issues, resulting in a revised and lower cost FID package.
Background
The project is a subsea tieback to an offshore gas platform and was at the end of the FEED (definition) phase. The non-operating JV partner requested Atteris to benchmark and review the cost and schedule estimates and challenge margins, design requirements and costs.
Work Performed by Atteris

Over a 2 week period, Atteris performed a thorough review of the cost and schedule estimates and delivered a study report with the following outcomes:

  • Benchmarked the project cost against a number of similar projects, normalising costs using the upstream capital cost index (UCCI) and by cost estimating the technical differences between the various projects
  • Identified and listed technical and schedule challenges which were used to drive the operating JV partner to reduce cost and improve schedule

Following the initial CAPEX and technical review, Atteris continued ad-hoc support to assist its client to finalise its internal FID package.

Download PDF
Share on facebook
Share on twitter
Share on linkedin
resources

Related Posts

Seawater Intake and Outfall
CASE STUDIES
Seawater Intake and Outfall
  • Tags:
  • Energy Transition
  • HDD
  • Shore Crossing
  • Tunnelling
Read More
Maitland to Burrup Subsea Corridor Assessment
CASE STUDIES
Maitland to Burrup Subsea Corridor Assessment
  • Tags:
  • Shore Approach
  • Shore Crossing
  • Subsea Pipeline
Read More
Simpson Pipeline – Decommissioning Stability Study
CASE STUDIES
Simpson Pipeline – Decommissioning Stability Study
  • Tags:
  • Decommissioning
  • On-bottom Stability
  • Subsea Pipeline
Read More